Weber JS is a special polymer-based joint compound for dry indoor areas. It is suitable for filling joints in drywall and mineral surfaces (plastered surfaces), as well as for general filling and use on painted surfaces. Mixing with water produces a ready-to-use filler.
• Coverage: approx. 0.1–0.2 kg/m² for joint filling
• Application temperature: at least +10°C
• Shelf life: 18 months (in dry conditions, in the original sealed packaging)
• Drying time (touch-dry): up to 1 day, depending on layer thickness, temperature, and ventilation
• Mix thickness: 1–2 mm
• Water content when mixing: 7 L/20 kg; 8–9 L/25 kg
• Binder: polymer adhesive
• Filler: limestone powder, particle size < 0.3 mm
• Pot life: 2 days when ready-mixed in a sealed container
• Color: white
Surface preparation: The substrate must be clean, solid, and free of dust. Remove any substances that could impair adhesion, such as paint, grease, and dust, from the substrate. When applying joint compound to painted surfaces, first sand the paint to a matte finish and then remove any dust. Check that screw and nail heads do not protrude above the surface of the board; level any protruding irregularities. Chisel out chipped or crumbling edges and corners with a drywall knife.
Mixing the mixture: Use clean water at room temperature for mixing. Water consumption is approximately 7 liters per 20 kg of dry mix. Mix twice using a whisk attached to a drill: the first mixing (about 2–3 minutes) is done with less water; let the mixture stand for 10–15 minutes; the second mixing (approx. 2–3 minutes) is done gently, and the remaining water is added. The pot life of the prepared mixture after adding water is 2 days (in a sealed container). During application, the temperature of the substrate, the mixture, and the room must be above +10°C.
Manual application:
1. Apply the joint compound with a wide trowel so that it generously fills the groove along the edge of the gypsum board.
2. Press the joint tape into the joint compound using, for example, a 75 mm wide steel trowel. Any excess joint compound that squeezes out from under the tape is smoothed over the joint. Apply the joint compound to the joint tape so that it completely fills the joint.
3. Level the joints flush with the drywall surface using a rigid putty knife. Once dry, the filled joints are finished (sanded) smooth using 120-grit or 150-grit sandpaper. In areas requiring a high-quality finish or that will be painted, the joints are filled and sanded twice.
4. The joints between walls, as well as the corners where walls meet ceilings, are also jointed using joint tape and joint compound. The joint tape is bent by hand along the crease on the tape to an angle of approximately 90° and pressed into the joint compound with a putty knife. Any putty squeezed out from under the tape is spread over the tape.
5. The heads of nails and screws are filled twice. Final sanding is performed once the filled joints have completely dried.
Surface Preparation: After sanding, wall and ceiling surfaces are ready for wallpapering or painting. For surfaces requiring a smooth finish, apply two coats of surface leveling compound.
Cleaning Tools: Wash tools with water immediately after use. Avoid allowing any mixture residue to enter the sewer system.
Safety Precautions: Irritates the eyes, respiratory tract, and skin. If necessary, wear safety goggles, a respirator, gloves, or protective cream. Avoid inhaling dust. If the mixture gets into your eyes, rinse immediately with plenty of water and consult a doctor if necessary.